North and Central American Projects

TECHNICAL

 

El Tornillito HEPP - Honduras

El Tornillito HEPP - Honduras


Feasibility study and preparation of EPC bid documents for a 160-MW 50-m head hydropower project on the Ulua River in NE Honduras. 

Hydrodynamic reservoir sedimentation modeling and identification of optimum sediment management strategies.

 

 

 

 

 

 

 

Tumarin Hydropower

Tumarin Hepp - Nicaragua


Preliminary assessment and pre-feasibility for the 160 MW Tumarin hydropower project on lower reaches of the Rio Grande de Matagalpa. 

The project features 24,000 m3/s design flood and 12,000 m3/s construction diversion flood.

 

 

 

 

 

 

 

Bonneville HEPPs - USA

Bonneville HEPPs - USA


Feasibility study of 8 small hydropower projects on Boise and Columbia Rivers in NW USA. The projects are to be developed around abandoned fish lifts and fish ladders. 

The study was performed in close cooperation with the USACE fishery biologists with the objective to avoid adverse impacts to functioning fish migration facilities.

 

 

 

 

 

 

La Vegona HEPP – Honduras

La Vegona HEPP – Honduras


Pre-feasibility study for 40 MW La Vegona project located 8 km downstream from the existing the 250 MW El Cajon hydroelectric plant. 

An innovative design developed on a new site selected by AquaE made the project attractive for private investors.

 

 

 

 

 

 

 

Patuca Hydroelectric Project - Honduras

Patuca Hydroelectric Project - Honduras


Pre-feasibility study of a 230 MW hydroelectric project on the Patuca River in eastern Honduras. 

Key aspects of the study included hydrology studies, geologic evaluation, environmental studies and negotiation of the project agreements.

 

 

 

 

 

 

 

Chamelecon HEPP - Honduras

Chamelecon HEPP - Honduras


Pre-feasibility and pre-investment study for 10 MW Chamelecon hydropower project in NW Honduras.

 

 

 

 

 

 

 

 

 

DEVELOPMENT

 

El Tornillito HEPP - Honduras

El Tornillito HEPP - Honduras


Review of the project constructability and implementation schedule, preparation of tender documents, owners requirement and technical specifications, project management plan and risk management plans for the 160 MW hydropower project on the Ulua River in Honduras.

 

 

 

 

 

 

 

Chaparral HEPP

Chaparral HEPP - El Salvador


Due diligence assessment of the project basic design, constructability and development risk for the 80 MW Chaparral project in El Salvador. 

The project features 4,000 m3/s construction diversion and annual flooding of the construction works.

 

 

 

 

 

 

 

El Trojes HEPP

El Trojes HEPP - Mexico


Preparation of Engineer-Procure-Construct (EPC) contract and assistance during contract negotiation for 8 MW hydroelectric project located on the Trojes River in the State of Jalisco.

 

 

 

 

 

 

 

Santa Maria HEPP - Panama

Santa Maria HEPP - Panama


Lead development role for 25 MW hydroelectric project located in Varaguas Province, 250 km west of Panama City. 

Prepared Due Diligence study of the project, investment analysis for investors and negotiated development rights for the project.

 

 

 

 

 

 

 

 

 

ENVIRONMENTAL

 

Tornillito HEPP – Honduras

Tornillito HEPP – Honduras


Feasibility ESIA and preparation of TOR for relevant baseline investigations for the 160 MW Tornillito project in Honduras. 

Screening, scoping of main issues and assessment of the alternatives in accordance with the Equator Principles.

 

 

 

 

 

 

 

PANAMA CANAL

PANAMA CANAL MASTER DEVELOPMENT PLAN 2005-2015 – Panama


Review of social, economic and cultural impacts and involuntary resettlement related to the Panama Canal expansion plan.

 

 

 

 

 

 

Back to Top